ARGE "Suspended Ceiling Assembly"
in Allianz Arena / Munich
September 2004 - June 2005
In collaboration with the company "3ker Industriekletterer" for the ARGE SUSPENDED CEILING ASSEMBLY and by order of the company "Gewerbeklettern Erfurt", we were contracted to put up steel frames and find appropriate industrial membranes.
More than 500 individual frames weighing 1.0-3.2 tonnes were placed in the suspended ceiling of the steel construction, assembled and fitted with technical membranes by over 200 workers in day-to-day operations until June 2005.